FPSO & offshore platforms
Lifeboats and davits, pumps and packages for FPSO Kaminho, FPSO P-78 and Hail & Ghasha.
From the FPSO pump skid to the refinery exchanger: hold points witnessed, blocking points flagged early, release only when every point is closed.
Lifeboats and davits, pumps and packages for FPSO Kaminho, FPSO P-78 and Hail & Ghasha.
Rotating and pressure equipment for gas plants and transmission lines, such as Dalma Gas and the West-to-East Pipeline.
Exchangers, vessels, pumps and electrical packages for refineries and process plants, such as BP GH Lingen and TÜPRAŞ.
Hydro test, run and performance tests, seal plans.
Mechanical run, vibration, noise, lube oil system.
Welding, NDT, hydro and helium leak tests, final dossier.
Fabrication surveillance, dimensional, coating, preservation.
Panels, motors, transformers, RM6 switchgear in hazardous areas.
Static and dynamic load tests, release gear, HPU.
AVIAMEI is the inspector on the shop floor: procedure revision checked before the test, readings recorded against the acceptance criterion, flash report the same evening, and an IRN only when nothing is left open.
Send your ITPOn behalf of DNV, Intertek, Worley, Applus+, Fulkrum and Intersica, or directly for EPCs and vendors.
Ambient photos: Unsplash. Mission photos on the home page: AVIAMEI, 2024–2026.
Inspections take place at the vendor’s workshop or test bench, in France and worldwide, before the equipment ships.
Yes. Most oil & gas missions are performed on behalf of an agency, in its report template and procedures.
Send the PO scope, ITP and vendor location. Reply within 24 working hours.